Hosting Gigawatts While Waiting on Fiber: The Connectivity Debt of America’s Data Center Boom

Big data centers are moving into small towns. We checked 25 recent and proposed projects against HighSpeedInternet.com coverage data and the latest public opinion research. Many host towns will have to give up land, power, and tax revenue. However, many of the homes in those towns still can’t even get fiber internet. How will small town America reconcile hosting gigawatts while waiting on fiber? The connectivity debt of the data center boom highlights infrastructure, social and political divides across the nation.

Key Takeaways

  • Construction has moved past the big hubs. JLL says 77% of the 66+ gigawatts (GW) under construction in North America is in newer “frontier” markets.
  • Host towns trail the hubs on fiber. In the typical host town we studied, fiber reaches 68% of homes. In five established hub towns, it reaches 88%.
  • Towns with weak fiber host 17.5 GW of planned power. That’s 9 of 22 active projects. Six of those towns have no home fiber in our listings.
  • Power costs are rising first. The price of grid capacity in the largest U.S. power market rose from $28.92 to $333.44 per megawatt-day in three auctions.
  • Broadband is missing from the local debate. Internet access didn’t come up in local news coverage of any of the 25 projects we reviewed.
  • Democrats campaigned against data centers in 2026. They won control of the House of Representatives and the Senate. New legislation may radically impact the future of these projects.

Data center building is taking over the frontier

For years, data centers clustered in a few metro areas with cheap land, strong fiber, and reliable power. Those markets are still growing fast. CBRE’s first-half 2026 data center report counts 10,903 megawatts (MW) running in the eight biggest North American markets. At full capacity, that’s about as much power as 8.8 million average U.S. homes use, based on household electricity data from the U.S. Energy Information Administration (EIA). The total is up 33.7% from a year earlier. Only 1.4% of that space is empty, and another 7,481 MW is under construction.

Northern Virginia is still the largest market, at 4,497 MW but Atlanta now leads in new construction, with nearly 2,900 MW underway.

Where data centers run today

Operating capacity in the eight primary U.S. markets, first half of 2026

Map of the eight primary U.S. data center markets. Northern Virginia is largest at 4,497 MW, followed by Atlanta at 1,803 MW and Dallas–Fort Worth at 1,433 MW.

Source: CBRE, North America Data Center Trends H1 2026. Circle size shows megawatts of operating capacity.

The bigger shift is happening outside those metros. JLL’s midyear 2026 report counts more than 66 GW under construction in North America. It says 77% of that is in frontier markets like West Texas, Ohio, Louisiana, Indiana, and the Carolinas.

Power is the main reason. “Power is the deciding factor,” says CBRE’s Stu Dyer of Northern Virginia. Developers go where they can get a grid connection or build their own power plants. Land, tax breaks, and how long it takes to get a utility hookup also shape where projects land, and JLL names land and hookup timelines as key limits in established markets.

The stakes are national. The Lawrence Berkeley National Laboratory estimates data centers used 4.4% of U.S. electricity in 2023. That share could reach 6.7%–12% by 2028.

Where the next wave is going

Recent, planned, blocked, and withdrawn projects, colored by fiber reach in the host town, with 50-mile rings around each project

Map of 25 data center projects with 50-mile rings. Projects in towns where fiber reaches under half of homes cluster in Pennsylvania, Maryland, Indiana, Wisconsin, Texas, Louisiana, and Arizona.

Source: HighSpeedInternet.com analysis of public project reports and provider coverage data, October 2026. Rings show a 50-mile radius. Bloomberg found more than 70% of grid price points with rising costs sit within 50 miles of major data center activity.

We use the term connectivity debt for a gap we can measure. Specifically, we’re looking at towns that host major digital infrastructure while many of their homes still can’t get fiber. Data centers don’t cause this gap. Their dedicated fiber connections are built for the data center, not for homes or other businesses nearby. But the gap shows where a town gives the most and gets the least connectivity back.
Two terms come up throughout this report:

  • Host town: the town where a new or planned data center campus sits, or the nearest town with a HighSpeedInternet.com page.
  • Hub town: a town in an established data center market that has hosted large facilities for years. We use five: Ashburn and Manassas, Virginia; Hillsboro, Oregon; Mesa, Arizona; and Council Bluffs, Iowa.

A large data center brings new or upgraded fiber routes, substations, and power lines to a town. That fiber serves the data center. On its own, it doesn’t reach the homes and businesses down the road.

To measure the gap, we matched each project’s host town to its HighSpeedInternet.com provider listings. Then we compared those towns with the five hub towns.

68%

Median fiber reach in 22 active host towns

88%

Median fiber reach in 5 established hub towns

13.6 GW

Planned in 6 towns with no home fiber listed

Six host towns have no home fiber provider in our listings. Together, they host 13.6 GW of planned power:

In Albany and Burlington, no wired option reaches more than 20% of homes. Most people there use fixed wireless, satellite, or 5G home internet.

The gap isn’t everywhere. Fiber reaches 99%–100% of homes in Saline, Michigan; Memphis, Tennessee; Abilene, Texas; and New Albany, Ohio. These are larger towns and suburbs where fiber arrived first. Data centers don’t create these gaps. But the newest projects are going to the smallest places, where the gaps already exist.

Fiber reach in 22 active host towns

Highest coverage of any one fiber provider in the host town, with planned project power, against the hub town median of 88%. Values match the scorecard below

Bar chart of fiber reach in 22 host towns. Six towns show no fiber, and three more fall below 50%. The hub town median is 88%.

Source: HighSpeedInternet.com provider coverage data (town pages updated August 2026). Project power comes from public announcements. Amarillo’s figure is Fermi America’s planned private power generation, not data center load.

Host townProjectPlanned powerStatusFiber reachDebt tier
Homer City, PAHomer City Energy Campus4.5 GWUnder constructionNone listed

High

Adamstown, MDQuantum Frederick2.4 GWUnder constructionNone listed

High

New Carlisle, INAWS Project Rainier2.2 GWOperating, expandingNone listed

High

Berwick, PAAWS Susquehanna campus1.9 GWApprovedNone listed

High

Albany, TXVantage Frontier (Stargate)1.4 GWUnder constructionNone listed

High

Burlington, TXStargate Milam County1.2 GWUnder constructionNone listed

High

Rayville, LAMeta Hyperion2.0 GWUnder construction30%

High

Tucson, AZProject Blue600 MWUnder construction43%

High

Port Washington, WIVantage Lighthouse (Stargate)1.3 GWUnder construction45%

High

Newnan, GAProject Sail900 MWApproved51%

Elevated

El Paso, TXMeta El Paso1.0 GWUnder construction57%

Elevated

Cheyenne, WYCrusoe and Tallgrass Project Jade1.8 GWPaused79%

Elevated

Bessemer, ALProject Marvel1.2 GW (est.)Approved87%

Low

Mount Pleasant, WIMicrosoft Fairwater900 MWOperating, expanding90%

Low

Southaven, MSxAI Colossus 21.3 GWOperating92%

Low

Lordstown, OHStargate Lordstown214 MW (est.)Under construction93%

Low

Las Cruces, NMProject Jupiter (Stargate)2.2 GWPermits paused by court94%

Low

Amarillo, TXFermi America HyperGridUp to 11 GW*Delayed99%

Low

Abilene, TXStargate Abilene1.2 GWPartly operating99%

Low

New Albany, OHMeta Prometheus1.0 GWOperating99%

Low

Memphis, TNxAI Colossus300 MWOperating99%

Low

Saline, MIStargate Saline Township1.4 GWUnder construction100%

Low

* Planned private power generation. Not scored: Prince William Digital Gateway in Gainesville, Virginia, which the courts blocked; Google’s Franklin Township proposal in Indianapolis, which Google withdrew; and Project Cumulus in St. Charles, Missouri, which its developer withdrew. For projects outside town limits, we used the nearest town with a HighSpeedInternet.com page.

The power bill arrives first

Host towns may wait years for better internet. Higher power costs show up much sooner, and they spread far beyond the host town.

The clearest sign comes from PJM Interconnection, the grid operator for 13 states and Washington, D.C. Its capacity auction pays power plants to be ready when demand peaks. Those costs flow into retail bills. The price rose more than elevenfold in three auctions.

PJM’s independent market monitor ties $16.6 billion in added costs to data center demand across two auctions. That includes $9.3 billion in 2025/26 and $7.3 billion in 2026/27. The 2027/28 auction hit its price cap, cost $16.4 billion, and still fell 6,517 MW short of PJM’s reliability target.

PJM capacity prices rose more than elevenfold in three auctions

Clearing price in dollars per megawatt-day, by delivery year: $28.92 (2024/25), $269.92 (2025/26), $329.17 (2026/27), and $333.44 (2027/28, price cap).

Bar chart of PJM capacity prices: $28.92 for 2024/25, $269.92 for 2025/26, $329.17 for 2026/27, and $333.44 for 2027/28, which hit the price cap.

Source: PJM Interconnection Base Residual Auction results.

Those wholesale costs are reaching households:

The cost question isn’t settled. A Berkeley Lab study found that from 2019 to 2024, states with the most new demand saw average prices fall after inflation. But that effect was weaker for home prices and may not last. A study by E3, paid for by Amazon, finds a 100 MW data center brings a utility about $3.4 million a year more than it costs to serve.

Regulators are also adding guardrails. Starting Jan. 1, 2027, Virginia puts customers of 25 MW or more in their own rate class, with minimum payments for the power they reserve. Ohio regulators ordered AEP Ohio to adopt new data center tariffs as well.

Our take: Whether data centers raise bills over time depends on how each state sets its rates. In PJM states today, the risk for households points up. And it’s arriving years before any connectivity benefit.

What communities are saying

Public opinion has turned fast. Three pollsters asked the same question more than once. In all three, opposition to a nearby data center passed 50% within about a year.

Opposition to a nearby data center passed 50% in under a year

Share who oppose a data center in or near their community, repeated national polls: Change Research 26% (March 2025), 52% (December 2025), 65% (April 2026); Heatmap and Embold 42% (August 2025), 51% (February 2026), 71% (May 2026); Emerson College Polling 42% (December 2025), 63% (July 2026).

Line chart. Change Research rose from 26% opposed in March 2025 to 65% in April 2026. Heatmap and Embold rose from 42% to 71%. Emerson rose from 42% to 63%.

Sources: Heatmap Pro and Embold Research (registered voters), Change Research (registered voters), and Emerson College Polling (likely voters). Dates are field dates.

Other national polls agree. Gallup finds 71% of Americans oppose an AI data center in their area. Only 53% oppose a nuclear plant. Half of opponents name the strain on water and energy, and 15% name higher utility bills. Among supporters, 55% name jobs.

The Pew Research Center finds 57% of Americans think data centers are bad for home energy costs. Just 5% think they help. And 69% say they’d be uncomfortable with a new data center nearby.

That opinion now shapes outcomes. Data Center Watch counts at least 75 projects worth about $130 billion blocked or delayed in the first quarter of 2026, a record. Another 45 projects worth about $68 billion followed in the second quarter. Here are recent examples from our dataset:

  • A Virginia appeals court upheld a ruling in March 2026 that voided the Prince William Digital Gateway rezoning.
  • Google withdrew its Indianapolis proposal in September 2025, just before a council vote.
  • St. Charles, Missouri, banned data centers in May 2026.
  • Port Washington, Wisconsin, voters now must approve data center tax breaks.
  • Coweta County, Georgia, residents filed 14,000+ signatures in October 2026 to force a vote.

We reviewed local news coverage of all 25 projects and coded each concern it reported. Twelve projects drew mostly opposition, 10 drew a mix, and one drew mostly support. Two had no clear public record. Water topped the list. Tax breaks or secrecy came next, then power bills.

Broadband didn’t come up in local news coverage of any of the 25 projects

Number of projects where each concern appeared in local news coverage

Bar chart. Water appeared in 18 of 25 projects, tax breaks or secrecy in 16, power bills in 15, air in 11, land in 10, noise in 7, and broadband in 0.

Source: HighSpeedInternet.com review of local news coverage of 25 projects, October 2026. A project can have more than one concern.

That zero matters. Supporters say data centers bring better broadband to their neighbors. But the proof so far is thin. One widely shared example is a developer’s prediction about a single Illinois project. Broadband isn’t part of the local debate as news outlets cover it, and we found no study that measures whether neighbors get better internet.

What it means for households and local businesses

Here’s what the coverage data, cost research, and public opinion tell us together.

1. High-debt towns face a double hit

Homes in the nine high-debt towns face rising power costs and few home internet choices at the same time. Fixed wireless, satellite, and 5G home internet can work well. But they rarely match fiber’s upload speeds or its room to grow. These households pay for the grid’s growth without a fiber upgrade to show for it.

2. Local businesses gain few jobs and no new fiber

Data centers create many construction jobs but few lasting ones. Virginia’s Joint Legislative Audit and Review Commission finds a typical facility employs about 50 full-time workers, and about half are contractors. That’s a small new customer base for local shops and services.

Local businesses also share in the rising power costs that flow into retail bills. And the fiber built for a data center doesn’t help them on its own. It’s a dedicated connection, the same way one business’s private fiber line doesn’t serve its neighbors. For a small business in a host town, the lasting benefit has to come from tax revenue and any connectivity commitments the town negotiates.

3. The fiber passes through, but it may not be allowed to stop

Some big tech contracts bar fiber builders from adding connections to towns along a route, Fierce Network reports. They can also bar spare conduit that could serve the community later. At least one major fiber company denies using these clauses. If they’re common, a town could host huge network capacity and still not be able to use it.

4. Connectivity is a missed bargaining chip

Towns already negotiate. Saline Township’s settlement includes about $14 million in community benefits. Frederick County’s draft deal promises $110 million. But broadband didn’t come up in local news coverage of any project we reviewed, which suggests it’s rarely on the table. That’s why we expect the debt to grow. Right now, 17.5 GW of planned power sits in towns where most homes can’t get fiber, with no agreement to change that.

What host communities can ask for

Any town can put these four requests on the table before it approves a project:

  1. Broadband in the community benefit agreement: Brookings recommends these agreements fund digital access.
  2. Connection points and spare conduit: New fiber routes should let local providers reach homes and businesses later.
  3. A public connectivity baseline: Measure local internet access before construction and again after the facility opens.
  4. Tax breaks tied to local benefits: Link abatements to measurable results, including connectivity.

Live near a data center? See what’s available at your address.

The political play against big data

Many Democrats made opposition to data centers, or calls for much tighter rules, part of their 2026 campaigns. CNBC reported that many Democrats campaigned against data centers nationwide, and in governor’s races, 26 candidates in 21 of the 36 states with contests ran on promises of anti-data center legislation

Several Democratic governors who had previously courted the industry also changed course. Axios reported in February that potential 2028 contenders who had bet big on data centers were retreating amid voter backlash. For example, Josh Shapiro called for more oversight after residents complained, and Wes Moore unveiled new guidelines data centers must meet to win his support.

Democrats weren’t uniform on how far to go. Some pushed outright pauses, while others focused on stronger rules. The gap between centrists and progressives appeared to be narrowing on the campaign trail, but with democrats now in control of the House and Senate it’s entirely possible that they take aim at data centers, potentially changing the trajectory of these initiatives completely. Only time and forth-coming legislative efforts, notwithstanding the executive branch’s right to veto, will tell the rest of this story.

Methodology

Projects: We reviewed 25 large data center projects from 2024 to 2026. They include projects that are announced, approved, under construction, recently opened, blocked, or withdrawn. We drew them from developer announcements, local news, and regulatory filings, current as of Nov. 2, 2026. Of the 25, 22 remain active. The list covers major projects in 17 states but isn’t a full count. Planned power is as reported, and we mark estimates.

Connectivity: Fiber reach is the highest coverage share of any one fiber provider on the host town’s HighSpeedInternet.com page. Those pages were last updated in August 2026. We left out mixed-technology and reseller listings. We measure coverage by town, not at the project site or by address. For projects outside town limits, we used the nearest town with a page. The hub comparison uses five established hub towns that don’t appear in the project list.

Public opinion: We coded local news coverage of each project into seven concern types. We also rated the overall reaction as mostly opposed, mixed, mostly supportive, or unclear. National poll figures come from each pollster’s published results.

Markets and costs: Market figures come from CBRE and JLL reports from 2026. The household comparison divides operating capacity by average U.S. household electricity use from EIA. Power cost figures come from the sources below.

Contributors

This report is a collaboration between the HighSpeedInternet.com editorial team and Clearlink Intelligence.

  • Michael De Medeiros
  • Kevin Parrish
  • Jessica Brooksby
  • Peter Christiansen
  • Hannah Haynes
  • Andrea Gutierrez-Prieto
  • Tim Tincher
  • Lindsay Smith
  • Katie Garza

How to cite this report

HighSpeedInternet.com, Clearlink Intelligence. “Hosting Gigawatts, Waiting on Fiber: The Connectivity Debt of America’s Data Center Boom.” [PUBLISH DATE].

Journalists, researchers, and policymakers may quote, chart, and link to this report with credit to HighSpeedInternet.com.

Media and research contact

Want the full dataset, data for your coverage area, or an interview with our analysts?

Tim Tincher, Senior Digital PR Specialist
[email protected]

Download the CSV

Sources