Hosting Gigawatts While Waiting on Fiber: The Connectivity Debt of America’s Data Center Boom
Nov 19, 2026 | Share
Data and Research, Industry Exclusive/Entertainment
Big data centers are moving into small towns. We checked 25 recent and proposed projects against HighSpeedInternet.com coverage data and the latest public opinion research. Many host towns will have to give up land, power, and tax revenue. However, many of the homes in those towns still can’t even get fiber internet. How will small town America reconcile hosting gigawatts while waiting on fiber? The connectivity debt of the data center boom highlights infrastructure, social and political divides across the nation.
Key Takeaways
- Construction has moved past the big hubs. JLL says 77% of the 66+ gigawatts (GW) under construction in North America is in newer “frontier” markets.
- Host towns trail the hubs on fiber. In the typical host town we studied, fiber reaches 68% of homes. In five established hub towns, it reaches 88%.
- Towns with weak fiber host 17.5 GW of planned power. That’s 9 of 22 active projects. Six of those towns have no home fiber in our listings.
- Power costs are rising first. The price of grid capacity in the largest U.S. power market rose from $28.92 to $333.44 per megawatt-day in three auctions.
- Broadband is missing from the local debate. Internet access didn’t come up in local news coverage of any of the 25 projects we reviewed.
- Democrats campaigned against data centers in 2026. They won control of the House of Representatives and the Senate. New legislation may radically impact the future of these projects.
Data center building is taking over the frontier
For years, data centers clustered in a few metro areas with cheap land, strong fiber, and reliable power. Those markets are still growing fast. CBRE’s first-half 2026 data center report counts 10,903 megawatts (MW) running in the eight biggest North American markets. At full capacity, that’s about as much power as 8.8 million average U.S. homes use, based on household electricity data from the U.S. Energy Information Administration (EIA). The total is up 33.7% from a year earlier. Only 1.4% of that space is empty, and another 7,481 MW is under construction.
Northern Virginia is still the largest market, at 4,497 MW but Atlanta now leads in new construction, with nearly 2,900 MW underway.
Where data centers run today
Operating capacity in the eight primary U.S. markets, first half of 2026
Source: CBRE, North America Data Center Trends H1 2026. Circle size shows megawatts of operating capacity.
The bigger shift is happening outside those metros. JLL’s midyear 2026 report counts more than 66 GW under construction in North America. It says 77% of that is in frontier markets like West Texas, Ohio, Louisiana, Indiana, and the Carolinas.
Power is the main reason. “Power is the deciding factor,” says CBRE’s Stu Dyer of Northern Virginia. Developers go where they can get a grid connection or build their own power plants. Land, tax breaks, and how long it takes to get a utility hookup also shape where projects land, and JLL names land and hookup timelines as key limits in established markets.
The stakes are national. The Lawrence Berkeley National Laboratory estimates data centers used 4.4% of U.S. electricity in 2023. That share could reach 6.7%ā12% by 2028.
Where the next wave is going
Recent, planned, blocked, and withdrawn projects, colored by fiber reach in the host town, with 50-mile rings around each project
Source: HighSpeedInternet.com analysis of public project reports and provider coverage data, October 2026. Rings show a 50-mile radius. Bloomberg found more than 70% of grid price points with rising costs sit within 50 miles of major data center activity.
We use the term connectivity debt for a gap we can measure. Specifically, weāre looking at towns that host major digital infrastructure while many of their homes still can’t get fiber. Data centers don’t cause this gap. Their dedicated fiber connections are built for the data center, not for homes or other businesses nearby. But the gap shows where a town gives the most and gets the least connectivity back.
Two terms come up throughout this report:
- Host town: the town where a new or planned data center campus sits, or the nearest town with a HighSpeedInternet.com page.
- Hub town: a town in an established data center market that has hosted large facilities for years. We use five: Ashburn and Manassas, Virginia; Hillsboro, Oregon; Mesa, Arizona; and Council Bluffs, Iowa.
A large data center brings new or upgraded fiber routes, substations, and power lines to a town. That fiber serves the data center. On its own, it doesn’t reach the homes and businesses down the road.
To measure the gap, we matched each project’s host town to its HighSpeedInternet.com provider listings. Then we compared those towns with the five hub towns.
68%
Median fiber reach in 22 active host towns
88%
Median fiber reach in 5 established hub towns
13.6 GW
Planned in 6 towns with no home fiber listed
Six host towns have no home fiber provider in our listings. Together, they host 13.6 GW of planned power:
- Homer City, Pennsylvania: a 4.5 GW gas-powered campus on a former coal plant site
- Adamstown, Maryland: the planned 2.4 GW Quantum Frederick campus
- New Carlisle, Indiana: Amazon’s Project Rainier, with seven buildings running on a planned 2.2 GW campus
- Berwick, Pennsylvania: the closest town to Amazon’s planned 1.9 GW campus at the Susquehanna nuclear plant
- Albany, Texas: near the 1.4 GW Vantage Frontier campus
- Burlington, Texas: near the 1.2 GW Stargate site in Milam County
In Albany and Burlington, no wired option reaches more than 20% of homes. Most people there use fixed wireless, satellite, or 5G home internet.
The gap isn’t everywhere. Fiber reaches 99%ā100% of homes in Saline, Michigan; Memphis, Tennessee; Abilene, Texas; and New Albany, Ohio. These are larger towns and suburbs where fiber arrived first. Data centers don’t create these gaps. But the newest projects are going to the smallest places, where the gaps already exist.
Fiber reach in 22 active host towns
Highest coverage of any one fiber provider in the host town, with planned project power, against the hub town median of 88%. Values match the scorecard below
Source: HighSpeedInternet.com provider coverage data (town pages updated August 2026). Project power comes from public announcements. Amarillo’s figure is Fermi America’s planned private power generation, not data center load.
| Host town | Project | Planned power | Status | Fiber reach | Debt tier |
|---|---|---|---|---|---|
| Homer City, PA | Homer City Energy Campus | 4.5 GW | Under construction | None listed | High |
| Adamstown, MD | Quantum Frederick | 2.4 GW | Under construction | None listed | High |
| New Carlisle, IN | AWS Project Rainier | 2.2 GW | Operating, expanding | None listed | High |
| Berwick, PA | AWS Susquehanna campus | 1.9 GW | Approved | None listed | High |
| Albany, TX | Vantage Frontier (Stargate) | 1.4 GW | Under construction | None listed | High |
| Burlington, TX | Stargate Milam County | 1.2 GW | Under construction | None listed | High |
| Rayville, LA | Meta Hyperion | 2.0 GW | Under construction | 30% | High |
| Tucson, AZ | Project Blue | 600 MW | Under construction | 43% | High |
| Port Washington, WI | Vantage Lighthouse (Stargate) | 1.3 GW | Under construction | 45% | High |
| Newnan, GA | Project Sail | 900 MW | Approved | 51% | Elevated |
| El Paso, TX | Meta El Paso | 1.0 GW | Under construction | 57% | Elevated |
| Cheyenne, WY | Crusoe and Tallgrass Project Jade | 1.8 GW | Paused | 79% | Elevated |
| Bessemer, AL | Project Marvel | 1.2 GW (est.) | Approved | 87% | Low |
| Mount Pleasant, WI | Microsoft Fairwater | 900 MW | Operating, expanding | 90% | Low |
| Southaven, MS | xAI Colossus 2 | 1.3 GW | Operating | 92% | Low |
| Lordstown, OH | Stargate Lordstown | 214 MW (est.) | Under construction | 93% | Low |
| Las Cruces, NM | Project Jupiter (Stargate) | 2.2 GW | Permits paused by court | 94% | Low |
| Amarillo, TX | Fermi America HyperGrid | Up to 11 GW* | Delayed | 99% | Low |
| Abilene, TX | Stargate Abilene | 1.2 GW | Partly operating | 99% | Low |
| New Albany, OH | Meta Prometheus | 1.0 GW | Operating | 99% | Low |
| Memphis, TN | xAI Colossus | 300 MW | Operating | 99% | Low |
| Saline, MI | Stargate Saline Township | 1.4 GW | Under construction | 100% | Low |
* Planned private power generation. Not scored: Prince William Digital Gateway in Gainesville, Virginia, which the courts blocked; Google’s Franklin Township proposal in Indianapolis, which Google withdrew; and Project Cumulus in St. Charles, Missouri, which its developer withdrew. For projects outside town limits, we used the nearest town with a HighSpeedInternet.com page.
The power bill arrives first
Host towns may wait years for better internet. Higher power costs show up much sooner, and they spread far beyond the host town.
The clearest sign comes from PJM Interconnection, the grid operator for 13 states and Washington, D.C. Its capacity auction pays power plants to be ready when demand peaks. Those costs flow into retail bills. The price rose more than elevenfold in three auctions.
PJM’s independent market monitor ties $16.6 billion in added costs to data center demand across two auctions. That includes $9.3 billion in 2025/26 and $7.3 billion in 2026/27. The 2027/28 auction hit its price cap, cost $16.4 billion, and still fell 6,517 MW short of PJM’s reliability target.
PJM capacity prices rose more than elevenfold in three auctions
Clearing price in dollars per megawatt-day, by delivery year: $28.92 (2024/25), $269.92 (2025/26), $329.17 (2026/27), and $333.44 (2027/28, price cap).
Source: PJM Interconnection Base Residual Auction results.
Those wholesale costs are reaching households:
- Virginia bills: A typical Dominion home bill rises $11.24 a month in 2026 and $2.36 more in 2027, per state regulators.
- Grid hookups: PJM customers paid for $4.3 billion in 2024 data center transmission connection costs, per the Union of Concerned Scientists.
- Wholesale prices: Near major data center activity, power cost up to 267% more in a month than five years earlier, Bloomberg found.
- Forecasts: Carnegie Mellon and NC State researchers project an 8% rise in U.S. power generation costs by 2030, and more than 25% in parts of Virginia.
- National prices: EIA expects home power to average 18.2 cents per kilowatt-hour (kWh) in 2026, up from 17.3 cents in 2025.
The cost question isn’t settled. A Berkeley Lab study found that from 2019 to 2024, states with the most new demand saw average prices fall after inflation. But that effect was weaker for home prices and may not last. A study by E3, paid for by Amazon, finds a 100 MW data center brings a utility about $3.4 million a year more than it costs to serve.
Regulators are also adding guardrails. Starting Jan. 1, 2027, Virginia puts customers of 25 MW or more in their own rate class, with minimum payments for the power they reserve. Ohio regulators ordered AEP Ohio to adopt new data center tariffs as well.
Our take: Whether data centers raise bills over time depends on how each state sets its rates. In PJM states today, the risk for households points up. And it’s arriving years before any connectivity benefit.
What communities are saying
Public opinion has turned fast. Three pollsters asked the same question more than once. In all three, opposition to a nearby data center passed 50% within about a year.
Opposition to a nearby data center passed 50% in under a year
Share who oppose a data center in or near their community, repeated national polls: Change Research 26% (March 2025), 52% (December 2025), 65% (April 2026); Heatmap and Embold 42% (August 2025), 51% (February 2026), 71% (May 2026); Emerson College Polling 42% (December 2025), 63% (July 2026).
Sources: Heatmap Pro and Embold Research (registered voters), Change Research (registered voters), and Emerson College Polling (likely voters). Dates are field dates.
Other national polls agree. Gallup finds 71% of Americans oppose an AI data center in their area. Only 53% oppose a nuclear plant. Half of opponents name the strain on water and energy, and 15% name higher utility bills. Among supporters, 55% name jobs.
The Pew Research Center finds 57% of Americans think data centers are bad for home energy costs. Just 5% think they help. And 69% say they’d be uncomfortable with a new data center nearby.
That opinion now shapes outcomes. Data Center Watch counts at least 75 projects worth about $130 billion blocked or delayed in the first quarter of 2026, a record. Another 45 projects worth about $68 billion followed in the second quarter. Here are recent examples from our dataset:
- A Virginia appeals court upheld a ruling in March 2026 that voided the Prince William Digital Gateway rezoning.
- Google withdrew its Indianapolis proposal in September 2025, just before a council vote.
- St. Charles, Missouri, banned data centers in May 2026.
- Port Washington, Wisconsin, voters now must approve data center tax breaks.
- Coweta County, Georgia, residents filed 14,000+ signatures in October 2026 to force a vote.
We reviewed local news coverage of all 25 projects and coded each concern it reported. Twelve projects drew mostly opposition, 10 drew a mix, and one drew mostly support. Two had no clear public record. Water topped the list. Tax breaks or secrecy came next, then power bills.
Broadband didnāt come up in local news coverage of any of the 25 projects
Number of projects where each concern appeared in local news coverage
Source: HighSpeedInternet.com review of local news coverage of 25 projects, October 2026. A project can have more than one concern.
That zero matters. Supporters say data centers bring better broadband to their neighbors. But the proof so far is thin. One widely shared example is a developer’s prediction about a single Illinois project. Broadband isn’t part of the local debate as news outlets cover it, and we found no study that measures whether neighbors get better internet.
What it means for households and local businesses
Here’s what the coverage data, cost research, and public opinion tell us together.
1. High-debt towns face a double hit
Homes in the nine high-debt towns face rising power costs and few home internet choices at the same time. Fixed wireless, satellite, and 5G home internet can work well. But they rarely match fiber’s upload speeds or its room to grow. These households pay for the grid’s growth without a fiber upgrade to show for it.
2. Local businesses gain few jobs and no new fiber
Data centers create many construction jobs but few lasting ones. Virginia’s Joint Legislative Audit and Review Commission finds a typical facility employs about 50 full-time workers, and about half are contractors. That’s a small new customer base for local shops and services.
Local businesses also share in the rising power costs that flow into retail bills. And the fiber built for a data center doesn’t help them on its own. It’s a dedicated connection, the same way one business’s private fiber line doesn’t serve its neighbors. For a small business in a host town, the lasting benefit has to come from tax revenue and any connectivity commitments the town negotiates.
3. The fiber passes through, but it may not be allowed to stop
Some big tech contracts bar fiber builders from adding connections to towns along a route, Fierce Network reports. They can also bar spare conduit that could serve the community later. At least one major fiber company denies using these clauses. If they’re common, a town could host huge network capacity and still not be able to use it.
4. Connectivity is a missed bargaining chip
Towns already negotiate. Saline Township’s settlement includes about $14 million in community benefits. Frederick County’s draft deal promises $110 million. But broadband didn’t come up in local news coverage of any project we reviewed, which suggests it’s rarely on the table. That’s why we expect the debt to grow. Right now, 17.5 GW of planned power sits in towns where most homes can’t get fiber, with no agreement to change that.
What host communities can ask for
Any town can put these four requests on the table before it approves a project:
- Broadband in the community benefit agreement: Brookings recommends these agreements fund digital access.
- Connection points and spare conduit: New fiber routes should let local providers reach homes and businesses later.
- A public connectivity baseline: Measure local internet access before construction and again after the facility opens.
- Tax breaks tied to local benefits: Link abatements to measurable results, including connectivity.
Live near a data center? See what’s available at your address.
The political play against big data
Many Democrats made opposition to data centers, or calls for much tighter rules, part of their 2026 campaigns. CNBC reported that many Democrats campaigned against data centers nationwide, and in governorās races, 26 candidates in 21 of the 36 states with contests ran on promises of anti-data center legislation
Several Democratic governors who had previously courted the industry also changed course. Axios reported in February that potential 2028 contenders who had bet big on data centers were retreating amid voter backlash. For example, Josh Shapiro called for more oversight after residents complained, and Wes Moore unveiled new guidelines data centers must meet to win his support.
Democrats werenāt uniform on how far to go. Some pushed outright pauses, while others focused on stronger rules. The gap between centrists and progressives appeared to be narrowing on the campaign trail, but with democrats now in control of the House and Senate itās entirely possible that they take aim at data centers, potentially changing the trajectory of these initiatives completely. Only time and forth-coming legislative efforts, notwithstanding the executive branchās right to veto, will tell the rest of this story.
Methodology
Projects: We reviewed 25 large data center projects from 2024 to 2026. They include projects that are announced, approved, under construction, recently opened, blocked, or withdrawn. We drew them from developer announcements, local news, and regulatory filings, current as of Nov. 2, 2026. Of the 25, 22 remain active. The list covers major projects in 17 states but isn’t a full count. Planned power is as reported, and we mark estimates.
Connectivity: Fiber reach is the highest coverage share of any one fiber provider on the host town’s HighSpeedInternet.com page. Those pages were last updated in August 2026. We left out mixed-technology and reseller listings. We measure coverage by town, not at the project site or by address. For projects outside town limits, we used the nearest town with a page. The hub comparison uses five established hub towns that don’t appear in the project list.
Public opinion: We coded local news coverage of each project into seven concern types. We also rated the overall reaction as mostly opposed, mixed, mostly supportive, or unclear. National poll figures come from each pollster’s published results.
Markets and costs: Market figures come from CBRE and JLL reports from 2026. The household comparison divides operating capacity by average U.S. household electricity use from EIA. Power cost figures come from the sources below.
Contributors
This report is a collaboration between the HighSpeedInternet.com editorial team and Clearlink Intelligence.
- Michael De Medeiros
- Kevin Parrish
- Jessica Brooksby
- Peter Christiansen
- Hannah Haynes
- Andrea Gutierrez-Prieto
- Tim Tincher
- Lindsay Smith
- Katie Garza

How to cite this report
HighSpeedInternet.com, Clearlink Intelligence. “Hosting Gigawatts, Waiting on Fiber: The Connectivity Debt of America’s Data Center Boom.” [PUBLISH DATE].
Journalists, researchers, and policymakers may quote, chart, and link to this report with credit to HighSpeedInternet.com.
Media and research contact
Want the full dataset, data for your coverage area, or an interview with our analysts?
Tim Tincher, Senior Digital PR Specialist
[email protected]
Sources
- CBRE, North America Data Center Trends H1 2026
- JLL, North America Data Center Report, Midyear 2026
- Lawrence Berkeley National Laboratory, 2024 United States Data Center Energy Usage Report
- U.S. Energy Information Administration, How Much Electricity Does an American Home Use?
- PJM Interconnection, 2027/2028 Base Residual Auction Report
- Monitoring Analytics, IMM Analysis of the 2026/2027 RPM Base Residual Auction
- Virginia State Corporation Commission, Final Order, Case No. PUR-2025-00058
- Union of Concerned Scientists, data center transmission costs in PJM
- Bloomberg, AI Data Centers Are Sending Power Bills Soaring
- Carnegie Mellon University and NC State, Open Energy Outlook
- U.S. Energy Information Administration, Short-Term Energy Outlook, October 2026
- Lawrence Berkeley National Laboratory, load growth and retail electricity prices
- E3, ratepayer study commissioned by Amazon
- Public Utilities Commission of Ohio, AEP Ohio data center tariff order
- Gallup, Americans Oppose Data Centers in Their Area
- Pew Research Center, data centers survey topline, September 2026
- Heatmap Pro and Embold Research, Change Research, and Emerson College Polling
- Data Center Watch, Q1 2026 and Q2 2026
- Fierce Network, hyperscaler fiber contracts
- Virginia Joint Legislative Audit and Review Commission, Data Centers in Virginia
- Brookings, community benefit agreements for data centers
- Badger Institute, data centers and connectivity
- Project-level sources for all 25 projects are in the downloadable dataset.
Author - Michael De Medeiros